Exley Science
Center, Science Library, Connector with Hall-Atwater - Scheduled Electrical
Power Outage December 26, 2009 through January 1, 2010
The main
electrical distribution equipment in Exley Science Center is nearing the end of
its useful life. Rather than suffer from an unplanned extended outage we
propose to replace this equipment during the Christmas Break. The replacement
of this equipment will require outages throughout the Exley Science Center,
Science Library and connector with Hall-Atwater. Therefore, the Exley
Science Center, Science Library and connector with Hall-Atwater will be closed
from 6 AM on Saturday, December 26, 2009 through 5 PM on Friday, January 1, 2010.
Please be sure that all electronic equipment is properly shutdown prior to
Saturday, December 26, 2009 at 4 AM. The details of the schedule are as
follows:
SHUTDOWN 1
Saturday, December 26, 2009, 6 AM to Noon
All electrical power shutdown, heat remains on, ITS Data Center on emergency
generator.
During this event
all of the lights and electrical power throughout the Exley Science Center,
Science Library and connector with Hall-Atwater will be shutdown, heat
throughout the building will be unaffected. ITS Data Center will run on
emergency generator. During this shutdown we will place all of ITS Data Center
on a back up generator so that all ITS Data Center services will be available.
At noon on Saturday December 26 we will return all power to the building. ITS
will have all of its power fed from a generator. The Academic Compute
Clusters will be down from Wednesday, December 23 through late morning Tuesday,
December 29.
All antennas will
be fed with generator power throughout this shutdown. All antennas will suffer
from a 30 minute shutdown in order to transfer them onto generator power. They
will remain unaffected until they are moved back to regular power.
ITS personnel
will have access to all ITS Data Center equipment without interruption should an
emergency arise.
SHUTDOWN 2
Sunday December 27, 2009 at 12 Noon THROUGH Monday December 28, 2009 6 PM
All electrical power shutdown, heat remains on, All of ITS Data Center on back
up generator
During this event
all of the lights and electrical power throughout the Exley Science Center,
Science Library and connector with Hall-Atwater will be shutdown. ITS Data
Center will be unaffected as it will be on a generator. On Monday, December 8,
2009 at 6 PM we will need to put ITS Data Center back on its own generator as we
migrate it to its final position, this will take 2 hours (academic computer
cluster shutdown). As of Monday, December 28, 2009 at 8 PM all of the lights
and power throughout Exley will be on its permanent power source. Heat
throughout the building will be unaffected.
All antennas will
be fed with generator power throughout this shutdown. All antennas will suffer
from a 30 minute shutdown in order to transfer them onto generator power. They
will remain unaffected until they are moved back to regular power. We
anticipate that we will move them from emergency power to regular power at
MIDNIGHT, Monday, December 28, 2009.
SHUTDOWN 3
Tuesday December 29, 2009 at 6 AM through Friday January 1, 2010 at 5 PM
All services in the Exley basement and connector with Hall-Atwater shutdown for
30 hours, ITS not impacted, heat is off throughout building
During this event
we will impact the power that feeds throughout the Exley basement, Science
Library, including lighting, and the connector with Hall-Atwater. These
services will be restored on a temporary basis Wednesday, December 30, 2009 at
NOON. We believe, but are not positive at this time, that the Exley science
tower will have lights and power throughout, with the exception of the basement,
ground floor and connector with Hall-Atwater.
During this
event, heat will be down throughout Exley Science Center, Science Library and
connector with Hall-Atwater. We will have a generator running pumps and fans to
prevent freezing and maintain temperatures at around 50 degrees.
ITS will not be
impacted at all during this time.
SHUTDOWN 4
Friday, January 1, 2010 from Noon to 5 PM
All services in Exley basement and connector with Hall-Atwater off for 5 hours
while final connections are made
Shutdown 3
continues but on Friday, January 1, 2010 from NOON to 5 PM we will shutdown the
power that throughout the Exley basement, Science Library, including lighting,
and the connector with Hall-Atwater that was fed on a temporary basis and make
its final connection to the new electrical gear.
As of 5 PM
Friday, January 1, 2010 it is anticipated that all shutdowns will be complete.
Please contact
Alan Rubacha at extension 3746 or
arubacha@wesleyan.edu.
|
|