Project Manager: Robert Schmidt
Design Builder:
Smith
Edwards Architects/ Enterprise Builders
Project Description: New Construction for Phase III
Construction Start Date: March 4, 2008 for Phase III
Current Status: Project Complete for Phase I and II, Phase III in
Permitting
Project Goals Phase III:
To create, thirty bedrooms in two residential structures. Each
unit will consist of living room, dining area, kitchen and full bath.
Six of the thirty bedrooms will be fully handicap accessible.Project Status
Phase III: August 2008
231 Pine Street project is substantially complete
19 Fountain Avenue construction is underway.
231 Pine Street - Concept Sketch below
Week of August 18, 2008:
Project is substantially complete

   
Above is 231 Pine Street as of August 18th, 2008 - project substantially
complete

Above is 231 Pine Street as of June 19th, 2008

Above is 231 Pine Street as of May 13th, 2008
19 Fountain Avenue - Concept Sketch below
Week of August 25th:
Framing
Week of September 1st: Roofing and Electrical Rough-in
Week of September 8th: Mechanical Rough-in


Above is 19 Fountain Avenue as of August 27th, 2008
Below: Student Senior Housing, Phase I,
Warren Avenue, front, looking East

Warren Street, view from the front porch of the recently completed addition for
the Freeman Athletic Center, looking West

Phase I, Fountain Avenue, front, looking West

Phase I and II, Typical living room / dining room

Phase I and II, Typical kitchen

|