Building Identification |
Dates Offline |
|
Malcolm X Sprinkler and Fire Alarm Installation:
This
work will involve the installation of a new water main that will cross
Washington Terrace.
|
5/26 - 8/8/03
|
|
200 High St Sprinkler and Fire Alarm Installation:
This work will involve the
installation of a new water main that will cross
High Street.
|
5/26 - 8/8/03
|
|
151 Church St Sprinkler and Fire Alarm Installation:
This work will involve the
installation of a new water main that will cross Church Street.
|
5/26 - 8/8/03
|
|
Foss 7 New Hot Water Heaters in Mechanical Room:
|
5/27 - 6/20/03
|
|
Foss 4 Sanitary Line Installation:
|
5/26 - 6/20/03
|
|
CFA Zilkha Gallery HVAC Upgrade, New
Finish Installation and Elevator Cylinder Replacement and elevator pump
changeout: Impacts use of Zilkha 106 and Zilkha 202.
|
5/26 -
10/15/03
|
|
CFA Art Workshops Fire Alarm Installation:
|
5/26 - 6/20/03
|
|
CFA Crowell Concert Hall Fire Alarm
Installation: |
5/26-5/28; 5/30-6/2, 6/3 (11:00
am)-6/20 & 8/4-8/22/03 |
|
CFA Music Studios Roof Hatch Access (platform and ladder installation):
|
5/26 - 6/20/03
|
|
CFA World Music Roof Repairs:
|
10/20 -
10/22/03
|
|
CFA Theater Stairwell Doors Replacement:
|
8/4 - 8/22/03
|
|
William
Street Highrise Apartments New Elevator Controller Installation: |
6/2 -
7/18/03 |
|
Park
Washington Apartments Elevator Cylinder Replacement: |
7/15 -
8/15/03 |
|
SLF
Woodframe Houses on MM Priority list: |
6/2 -
8/8/03 |
|
William
Street Lowrise Unit E shower enclosure repair: |
6/2 -
6/20/03 |