Location |
Estimated Start Date |
Estimated Completion |
Punch List Completion Date |
|
Priority items Managed by Roseann Sillasen
x3476 |
|
|
|
|
Lowrise B Interior
Maintenance Fire Alarm
installation complete 6/10. Electrical, bathroom plumbing and wall patching
in progress. |
5/24/04 |
7/30/04 |
9/3/04 |
|
|
|
|
|
|
Lowrise B Water Main Installation for Fire Sprinkler
System Excavation work to begin at Church St down
Hotchkiss to Building B for new water main w/o 7/5. Sprinkler piping 37%
complete. |
6/21/04 |
6/25/04 |
9/3/04 |
|
|
|
|
|
|
Foss #4 High Voltage
Oil Fuse Change Out Power outage scheduled 6/17
& 6/18 |
6/14/04 |
6/18/04 |
6/19/04 |
|
|
|
|
|
|
Foss #5 High Voltage
Oil Fuse Change Out
Power outage scheduled 6/10 & 6/11 |
6/7/04 |
6/11/04 |
6/12/04 |
|
|
|
|
|
|
107 High Street Roof
Replacement Roof complete. Pending gutter
installation. |
6/18/04 |
6/24/04 |
7/14/04 |
|
|
|
|
|
|
151 Church Street
Roof Replacement |
TBD |
TBD |
8/30/04 |
|
|
|
|
|
|
128 Pearl Street
Rain Leader Connection to City Storm Sewer System
Regrading required. |
6/1/04 |
6/2/04 |
6/30/04 |
|
|
|
|
|
|
Butterfield Cooling
Tower Replacement All air conditioning
supply is required to be shutdown for this work to occur. System drain down
7/9. Demolition of cooling tower 7/12. Steel erection begins 7/14. |
7/8/04 |
8/6/04 |
9/22/04 |
|
|
|
|
|
|
230 Washington Street
Boiler Replacement Abatement completed 6/8/04.
Room firesafed. New boiler in process of being built. |
6/7/04 |
7/23/04 |
8/30/04 |
|
|
|
|
|
|
Freeman
Strainer/Valves Grodsky Mechanical to perform
work. Eros Pools to assist with pool draining and water circulation during
shutdown. |
8/9/04 |
8/20/04 |
8/20/04 |
|
|
|
|
|
|
Freeman Track Repair
By Dalton Bubbling areas to be cut and resecured
to surface. Steeplechase pit slice to be repaired. |
7/12/04 |
7/14/04 |
7/27/04 |
|
|
|
|
|
|
Vine Street Tennis
Courts 9-16 By Dalton |
7/1/04 |
7/5/04 |
7/27/04 |
|
|
|
|
|
|
163 High Street
Window & Floor Replacement/ Wall Repairs
Demo complete, new ceilings installed. Subfloor for new flooring in
progress. Fire Alarm complete. Windows to be installed w/o 7/26. |
5/24/04 |
8/6/04 |
8/25/04 |
|
|
|
|
|
|
163 High Street Water Main
Installation For Fire Sprinkler System.
Sprinkler installation on going. |
6/7/04 |
7/9/04 |
8/25/04 |
|
|
|
|
|
|
34 Lawn Avenue
Kitchen Maintenance
Abatement performed 6/1-6/4. Floor installation
complete. Electrical in progress. Cabinet
installation in progress. Window to be installed w/o 7/26. |
5/31/04 |
8/6/04 |
8/15/04 |
|
|
|
|
|
|
34 Lawn Avenue
Exterior Painting
Exterior power wash performed 6/7/04. Painting in
progress beginning w/o 6/21/04. |
6/18/04 |
6/30/04 |
9/27/04
pending storm window |
|
|
|
|
|
|
170 College Street
Bathroom & Window Repairs Demo complete. New
walls installed. Subfloor installed. Shower unit installed. |
5/31/04 |
7/12/04 |
8/7/04 |
|
|
|
|
|
|
Park Washington
Elevator Pump Replacement Otis Elevator to perform
work. |
7/6/04 |
7/9/04 |
7/11/04 |
|
|
|
|
|
|
154 Church Street
Roof Replacement In progress by Eagle Roofing.
Gutters pending. |
6/28/04 |
7/2/04 |
8/30/04 |
|
|
|
|
|
|
30 Fountain Avenue
Windows/ Porches Porch
rebuilds complete. Painting to be performed. Windows to be installed w/o
7/26. |
5/24/04 |
8/6/04 |
8/15/04 |
|
|
|
|
|
|
125 Mt Vernon
Electrical
Client meeting 6/18. Electrical work in progress. Work
may continue with house occupied. |
6/24/04
8/17/04
|
7/2/04
8/27/04
|
8/15/04 |
|
|
|
|
|
|
125 Mt Vernon Roof
Replacement 7:00 am start time. To be completed
7/2. Gutter work pending. |
6/24/04 |
7/2/04 |
8/15/04 |
|
|
|
|
|
|
135 Mt Vernon
Electrical Upgrade
Electrical work completed. Final patch and paint in
progress. |
5/25/04 |
6/28/04 |
8/15/04 |
|
|
|
|
|
|
10 Brainerd Avenue
Roof Replacement
Rake edge to be completed. Gutter work pending |
6/7/04 |
7/6/04 |
8/15/04 |
|
|
|
|
|
|
130 Mt Vernon Roof
Replacement 8:00
am start time. Gutter work pending. |
6/24/04 |
7/7/04 |
8/15/04 |
|
|
|
|
|
|
146 Cross Street
Porch Roof Replacement
In progress. Gutter work pending. |
6/24/04 |
7/9/04 |
8/1/04 |
|
|
|
|
|
|
146 Cross Street
Porch Repair Gutter work pending |
5/24/04 |
7/6/04 |
8/1/04 |
|
|
|
|
|
|
146 High Street Roof
Replacement Gutter work pending. |
6/11/04 |
7/7/04 |
8/1/04 |
|
|
|
|
|
|
268 Court Street Roof
Replacement Issues obtaining terra cotta
shingle color. |
6/28/04 |
7/1/04
TBD
|
8/15/04 |
|
|
|
|
|
|
258 Court Street Roof
Replacement Perform masonry work to chimneys
prior to roofing replacement |
6/28/04 |
7/12/04 |
8/30/04 |
|
|
|
|
|
|
162 Cross Street
Exterior Paint |
7/19 |
7/2304 |
8/20/04 |
|
|
|
|
|
|
65 Lawn Avenue
Exterior Paint |
6/28/04 |
7/9/04 |
8/30/04 |
|
|
|
|
|
|
PAC Elevator Controller Modernization
Thyssen Elevator on site. |
6/28/04 Elevator out of service |
7/16/04 |
7/21/04 |
|
|
|
|
|
|
Science Tower Areaway Repair (Lawn Avenue)
This is a noise producing project. Hammer drilling, sawing, diamond cutting
into concrete walls. Waterproofing in progress |
6/2/04 |
7/18/04 |
8/30/04 |
|
|
|
|
|
|
CFA Music Studios Elevator Cylinder & Pump Replacement
Final inspection by elevator inspection. |
5/24/04 |
6/18/04 |
6/20/04 |
|
|
|
|
|
|
VVO Roof Replacement Crane,
dumpsters and tar pot to be placed on North side of building. Non-toxic
fumes will be generated during this work. |
6/28/04 |
7/2/04 |
8/5/04 |
|
|
|
|
|
|
|
|
|
|
|
Priority items Managed by
Barbara Spalding x3780 |
|
|
|
|
202 Washington Street Fire Alarm & Sprinkler Upgrade
In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
|
|
316 Washington Street Fire Alarm Upgrade and New Sprinkler
System In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
|
|
65 Pearl Street Fire Alarm Upgrade and New Sprinkler
System In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
|
|
1 Vine Street Fire Alarm Upgrade and New Sprinkler System
In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
|
|
230 Washington Street Fire Alarm & Sprinkler Upgrade
In progress |
5/24/04 |
7/30/04 |
9/30/04 |