Building |
Room # |
Description of Work |
|
#208 |
|
|
|
Public Affairs Center |
PAC
421 |
Patch plaster at northwest corner of wall. Paint north and west walls and
trim.
Clean carpet by extraction method.
Refinish seminar room table.
Increase lighting. Install 4 additional ceiling fixtures. Zone switching. |
|
|
PAC136 |
Paint walls, trim, door and frame. Match existing color scheme. |
|
|
PAC125 |
Paint walls, trim, door and frame. Match existing color scheme. |
|
|
PAC104 |
Paint walls, trim, door and frame. Match existing color scheme. |
|
|
PAC411 |
Increase lighting. Install 4 additional ceiling fixtures. Zone switching. |
|
|
PAC001 |
Clean carpet by extraction method.
Repair mechanical mecco shades. |
|
Fisk Hall |
Fisk 115 |
Replace all discolored ceiling tiles with matching ceiling tile profile. |
|
|
Fisk 114 |
Replace all discolored ceiling tiles with matching ceiling tile profile |
|
|
Fisk 116 |
Paint walls, trim, door and frame. Match existing color scheme. |
|
|
FISK312 |
Replace all discolored ceiling tiles with matching ceiling tile profile |
|
Science Center |
SC137 |
Clean carpet by extraction method.
Zone existing fluorescent lighting to 2 zones. Provide switching at front of
room. |
|
|
SC139 |
Clean carpet by extraction method.
Zone existing fluorescent lighting to 2 zones. Provide switching at front of
room. |
|
|
SC141 |
Clean carpet by extraction method.
Zone existing fluorescent lighting to 2 zones. Provide switching at front of
room. |
|
|
SC121 |
Reinstall tablet arm chairs. Secure to floor. Provide new floor bolts. |
|
|
SC109 |
Clean carpet by extraction method. |
|
|
SC58 |
Clean carpet by extraction method. Replace bleached areas if unable to
clean satisfactorily. |
|
Shanklin Hall |
SHAN107 |
Clean carpet by extraction method. |
|
Hall-Atwater |
HA84 |
Clean carpet by extraction method. |
|
Butterfield A |
Butt A413 |
Install ceiling tile (1 missing) |
|
Butterfield C |
Butt C314 |
Replace discolored ceiling tiles. Paint walls, trim, doors. |
|
|
|
|
|
#66 |
|
|
|
Center for the Arts |
|
|
|
Dance Studios |
East Room |
Install electrical for new a/v installation.
Repair room filtering shade.
Paint all surfaces; walls, window and door trim, doors, FCUs.
Refinish wood floor. |
|
|
001 |
Install electrical for new a/v installation.
Paint all surfaces; walls, door trim, doors, etc.
Refinish wood floor.
Install new entry doors with lites. |