Item
Priority #
|
Building Address |
Building Name/Tenant |
Proposed Maintenance |
Segment |
|
1 |
Various |
Campus |
Removal of 5 underground oil storage tanks, CHEFA
required - COMPLETE
|
Infrastructure |
|
2 |
Washington Terr |
CFA Complex |
Install fire alarm system - COMPLETE
|
A&AF |
|
3 |
159 High St |
159 High St |
Add fire sprinkler system, door closers, extend
handrails. Approx. cost |
RP |
|
4 |
22/24 - 36 Brainerd Ave
|
22/24 - 36 Brainerd |
Replace doors/frames with fire rated.
Extend
handrails to be code compliant. Fire protection in basements. Fire Dept.
mandate. Approx. Cost |
RP |
|
5 |
200 Church St |
Chi Psi |
Upgrade Electrical System - COMPLETE
|
SLF |
|
6 |
280 William St |
CPP |
Roof repairs to address active leaks
- COMPLETE |
A&AF |
|
7 |
327 High St |
Infirmary & Guest House |
Replace doors per fire Marshall |
A&AF |
|
8 |
200 Church St |
Chi Psi |
Install Sprinkler System - COMPLETE
|
SLF |
|
9 |
Various |
Grad/Fac/Staff properties |
Asbestos Abatement |
RP |
|
10 |
272-278 Court St |
Wes Court Apts |
Paint all windows and trim
|
RP |
|
11 |
All Houses |
All Houses |
Secure Basements & Attics -
COMPLETE
|
SLF-WF |
|
13 |
200 Church St |
Chi Psi |
Replace Bedroom Doors & Locksets -
COMPLETE
|
SLF |
|
14 |
280 William St |
CPP |
Improve ventilation, provide cooling within space
- COMPLETE
|
A&AF |
|
15 |
200 High St |
Eclectic |
Replace Bedroom Doors & Locksets -
COMPLETE
|
SLF |
|
16 |
134 Cross St |
134 Cross St |
New Roof & Gutter, Paint House -
COMPLETE
|
SLF-WF |
|
17 |
159 Vine St |
159 Vine St |
Repair Back Porch, Upgrade Smoke Detectors to Code,
Paint House - COMPLETE
|
SLF-WF |
|
18 |
163 Vine St |
163 Vine St |
Repoint Chimney, Upgrade Smoke Detectors to Code,
Paint House - COMPLETE
|
SLF-WF |
|
19 |
166 Cross St |
166 Cross St |
New Roof, Paint House, Upgrade Interior Lights, Pave
Driveway, Repair Stucco - COMPLETE
|
SLF-WF |
|
20 |
188 Cross St |
188 Cross St |
Paint House, Repair Porch And Roof, Repair Front
Steps, Install Gutters Around House - COMPLETE
|
SLF-WF |
|
21 |
343 Washington Terr |
East Asian Studies |
Install fire alarm system - COMPLETE
|
A&AF |
|
22 |
271 Court St |
English |
Install fire alarm system - COMPLETE
|
A&AF |
|
23 |
212 College St |
Human Resources |
Install fire alarm system - COMPLETE
|
A&AF |
|
24 |
207 High St |
Judd Hall |
Install fire alarm system / Work
to begin December 15, 2002 |
A&AF |
|
25 |
237 High St |
North College |
Install fire alarm system / Elevator
Recall - COMPLETE
|
A&AF |
|
26 |
300 High St |
Romance Languages |
Install fire alarm system - COMPLETE
|
A&AF |
|
27 |
318/330 High St |
University Relations |
Repair/replace walks at 318/pave worn corner of drive
at 330 - COMPLETE |
A&AF |
|
29 |
167 Vine St |
167 Vine St |
Powerwash and Repoint Brick, Repair Porch, Install
New Interior Lights, Remove Vines From House, Upgrade Smoke Detectors to Code
- COMPLETE
|
SLF-WF |
|
30 |
171 Vine St |
171 Vine St |
Paint House, New Interior Lights, Upgrade Smoke
Detectors to Code - COMPLETE
|
SLF-WF |
|
31 |
23 Vine St |
23 Vine St |
Wash or Spray Paint Exterior, Upgrade Smoke
Detectors to Code - COMPLETE
|
SLF-WF |
|
32 |
54 Home Ave |
54 Home Ave |
Paint House, New Roof, Repair Porch -
COMPLETE
|
SLF-WF |
|
33 |
7 Vine St |
7 Vine St |
Paint House, Repair Exterior Steps, Upgrade
Interior Lighting, Remove Shrubs Around Bldg, Upgrade Driveway - COMPLETE
|
SLF-WF |
|
34 |
9 Vine St |
9 Vine St |
Upgrade Interior Lights, Paint House, Upgrade Landscape, Remove Shrubs - COMPLETE
|
SLF-WF |
|
35 |
Church/Pine |
Foss Hill |
Install Fire Emergency Egress - Unit II
- COMPLETE
|
SLF |
|
36 |
161 Cross St |
Freeman AC |
Exterior concrete repairs - COMPLETE
|
SLF |
|
37 |
William St |
Lowrise |
Hot water line replacement - COMPLETE
|
Infrastructure |
|
38 |
11 Vine St |
11 Vine St |
Paint House, Repair Back Porch, Upgrade Interior
Lights - COMPLETE
|
SLF-WF |
|
39 |
125 Cross St |
125 Cross St |
Paint House, Upgrade Interior Lights, Remove Large
Shrubs - COMPLETE
|
SLF-WF |
|
40 |
168 Cross St |
168 Cross St |
Paint House, Remove or Trim Trees, Upgrade Interior
Lights, replace casement windows - COMPLETE
|
SLF-WF |
|
41 |
316 Washington St |
316 Washington St |
Repair Front Porch & Paint Exterior
- COMPLETE
|
SLF-WF |
|
42 |
34/36 Fairview |
34/36 Fairview |
Raze building - Includes abatement |
RP |
|
43 |
344 Washington St |
344 Washington St |
Repair rotted metal tread and remove and replace
landing - COMPLETE
|
SLF |
|
44 |
280 William St |
CPP |
Combustion control modifications, Boilers #1 &
#2 - COMPLETE
|
Infrastructure |
|
45 |
Church St |
Davenport Campus Center |
Repair Drainage Outside of Gr. Fl. Entrance
- COMPLETE
|
SLF |
|
46 |
202 Washington St |
Gingerbread House |
Replace flat roof |
SLF |
|
47 |
237 Church St |
Hall Atwater |
Install air flow meters on fume hoods -
COMPLETE
|
A&AF |
|
48 |
238 Church St |
PAC |
Repair steps north east corner -
COMPLETE
|
A&AF |
|
49 |
238 Church St |
PAC |
Repair walk north side - COMPLETE
|
A&AF |
|
50 |
56 Hamlin |
Physical Plant |
Repair roof leaks and rotted wooden floor boards at
elevator - COMPLETE
|
PP |
|
51 |
1 Vine St |
1 Vine St
|
Relocate Existing Basement Laundry Equip.
- COMPLETE
|
SLF-WF |
|
52 |
186 Cross St |
186 Cross St |
Paint House, Remove Old Fence -
COMPLETE
|
SLF-WF |
|
53 |
324 Washington St |
324 Washington St |
Paint Exterior - COMPLETE
|
SLF-WF |
|
54 |
343 High St |
CAAS |
Repair walk
- COMPLETE |
A&AF |
|
55 |
283 Washington Terr |
CFA R |
Replace HVAC system servicing dance studio
- COMPLETE
|
A&AF |
|
56 |
271 Court St |
English |
Replace carpet & pad - COMPLETE
|
A&AF |
|
57 |
Various |
Fac/Grad |
Repair and replace porches - 5 year plan |
RP |
|
58 |
Various |
Fac/Grad |
Repair and replace roofs - 5 year plan
- COMPLETE
|
RP |
|
59 |
William St |
Lowrise |
Repair steps & install handrails -
COMPLETE
|
SLF |
|
60 |
William St |
Lowrise-Unit # E |
Renovation- Interior & Exterior -
COMPLETE
|
SLF |
|
61 |
McMonaughy Dr |
Mocon |
Replace Loading Dock Doors - COMPLETE
|
SLF |
|
62 |
McMonaughy Dr |
Mocon |
Replace Divider Curtain - COMPLETE
|
SLF |
|
63 |
238 Church St |
PAC |
Repair water main - COMPLETE
|
A&AF |
|
64 |
52 Home Ave |
52 Home Ave |
Paint House - COMPLETE
|
SLF-WF |
|
65 |
Various |
Campus |
Clean Leaves from Gutters |
SLF-WF |
|
66 |
280 William St |
CPP/Butterfield |
Phase I Utility Master Plan - CHEFA -
COMPLETE
|
Infrastructure |
|
67 |
200 College St |
French House |
Paint Exterior, repair front porch -
COMPLETE
|
SLF-WF |
|
68 |
56 Hamlin |
Physical Plant |
Repair loading dock door - COMPLETE
|
PP |
|
69 |
350 High St |
Russell House |
Repair walk - COMPLETE
|
A&AF |
|
70 |
265 Church St |
Science Center |
Replace Halon fire suppression in computer room
- COMPLETE
|
A&AF |
|
71 |
240 Court St |
240 Court St |
Renovate Interior - COMPLETE
|
SLF |
|
72 |
Lawn Ave |
Butterfield C |
Repair steps
- COMPLETE |
SLF |
|
73 |
280 William St |
CPP |
Repair breaching Boiler # 1 - COMPLETE
|
A&AF |
|
74 |
280 William St |
CPP |
Install catwalk for Boiler Cleaning -
COMPLETE
|
A&AF |
|
75 |
Foss Hill |
Foss 2 |
Renovate walk - COMPLETE
|
SLF |
|
76 |
High St |
High St |
Repair/replace walks - COMPLETE
|
A&AF |
|
77 |
McMonaughy Dr |
Mocon |
Paint Interior - COMPLETE
|
SLF |
|
78 |
237 High St |
North College |
Replace fan coils 3rd & 4th floors
- COMPLETE
|
A&AF |
|
79 |
237 Church St |
Old Power Plant |
Remedial repairs to valves & asbestos abatement
- COMPLETE
|
Infrastructure |
|
80 |
281 High St |
Anthropology |
Install steam boiler - COMPLETE
|
A&AF |
|
81 |
Various |
Campus |
Balance chilled water loop |
Infrastructure |
|
82 |
Various |
Campus |
Repair Plaster Walls |
SLF-WF |
|
83 |
Washington Terr |
CFA P Theater |
Inspect and certify theater rigging -
COMPLETE
|
A&AF |
|
84 |
280 William St |
CPP |
Clean boilers - COMPLETE
|
Infrastructure |
|
85 |
Church/Pine |
Foss 9 |
Provide Handicapp Access-Entry,Bathroom, Lounge,
Bedroom & Laundry - COMPLETE
|
SLF |
|
86 |
161 Cross St |
Freeman AC |
Re-stripe Outdoor Track - COMPLETE
|
SLF |
|
87 |
McMonaughy Dr |
Mocon |
Replace Skylight - COMPLETE
|
SLF |
|
88 |
Church St |
PAC |
Hydraulic cylinder replacement -
COMPLETE
|
PP |
|
89 |
56 Hamlin |
Physical Plant |
Upgrade Men's & Women's Rooms -
COMPLETE
|
PP |
|
90 |
Various |
Campus |
Purchase and installation of two blue light
telephones on stanchions - COMPLETE
|
PP |
|
91 |
280 William St |
CPP |
Install non chemical water treatment on tower
- COMPLETE
|
Infrastructure |
|
92 |
Church St |
Davenport Campus Center |
Replace Air Handler at P.Office -
COMPLETE
|
SLF |
|
93 |
230 Washington St |
Greenhouse Residence |
Move laundry from basement to 1st floor
- COMPLETE
|
SLF |
|
94 |
237 High St |
North College |
Insulate piping in walls & ceilings
- COMPLETE
|
A&AF |
|
95 |
237 High St |
North College |
Replace converters & AHU's, install DDC
- COMPLETE
|
A&AF |
|
96 |
238 Church St |
PAC |
Repair bluestone steps north east corner to drive
- COMPLETE
|
A&AF |
|
97 |
265 Church St |
Science Center |
Repair wall - COMPLETE
|
A&AF |
|
98 |
96 Lawn Ave |
96 Lawn Ave |
Repair bank |
SLF-WF |
|
99 |
Various |
Campus |
Roof replacement/repair to be specified
- COMPLETE
|
A&AF |
|
100 |
283 Washington Terr |
CFA P Theater |
Lighting support and ladder cage -
COMPLETE
|
A&AF |
|
101 |
283 Washington Terr |
CFA R |
Replace dance floor - COMPLETE
|
A&AF |
|
102 |
280 William St |
CPP |
Burner modifications boiler #1 & #2
- COMPLETE
|
Infrastructure |
|
103 |
222 Chruch St |
Davenport Campus Center |
Hydraulic cylinder replacement -
COMPLETE
|
PP |
|
104 |
Wyllys St |
Fayerweather Gym |
Replace all malfunctioning plumbing fittings
- COMPLETE
|
SLF |
|
105 |
Freeman AC |
Freeman AC |
Women's Hockey Locker room bathroom repairs and new
rubber matting - COMPLETE
|
SLF |
|
106 |
161 Cross St |
Freeman AC |
Replace doors and locksets throughout building
- COMPLETE
|
SLF |
|
107 |
202 Washington St |
Gingerbread House |
Remove garage/install fence - COMPLETE
|
SLF |
|
108 |
McMonaughy Dr |
Mocon |
Upgrade Lighting in Service Area -
COMPLETE
|
SLF |
|
109 |
238 Church St |
PAC |
Replace built in box gutter
Deferred |
A&AF |
|
110 |
229 High St |
South College |
Repair HVAC piping insulation -
COMPLETE
|
A&AF |
|
111 |
Church St |
VVO |
Repair roof - COMPLETE
|
A&AF |
|
112 |
McMonaughy Dr |
VVO/Mocon |
Renovate drive to allow fire truck access and
install chillded water lines to Mocon while pavement is removed. - COMPLETE
|
A&AF |
|
113 |
Church St |
"C" Lot |
Repair upper "C" Lot, connect drain to
storm - COMPLETE
|
A&AF |
|
114 |
156 High St |
156 High St |
Repair/widen/curb drive
- COMPLETE |
SLF |
|
115 |
Various |
Campus |
Remove dead/dying Hemlocks - COMPLETE
|
A&AF |
|
116 |
Foss Hill |
Foss 1 |
Renovate patio - COMPLETE
|
SLF |
|
117 |
161 Cross St |
Freeman AC |
Repair and crown Lower Long Lane 1 Field
- COMPLETE
|
SLF |
|
118 |
95 Pearl St |
Humanities |
Repair/replace bluestone walk -
COMPLETE
|
A&AF |
|
119 |
207 High St |
Judd Hall |
Hydraulic Cylinder Replacment -
COMPLETE
|
PP |
|
120 |
56 Hamlin |
Physical Plant |
Replace windows - COMPLETE
|
PP |
|
|
178 Cross St |
PIMMS |
Install chimney liner - COMPLETE
|
A&AF |
|
123 |
281 High St |
Anthropology |
Install chimney liner - COMPLETE |
A&AF |
|
124 |
167/169 High St |
Argus |
Install chimney liner - COMPLETE
|
A&AF |
|
125 |
Washington Terr |
CFA Complex |
Replace isolation and control valves -
COMPLETE
|
A&AF |
|
126 |
280 William St |
CPP |
Equipment trolley - COMPLETE
|
A&AF |
|
127 |
301 High St |
Davison Art Center |
Install chimney liner -COMPLETE
|
A&AF |
|
128 |
343 Washington Terr |
East Asian Studies |
Install chimney liner - COMPLETE
|
A&AF |
|
130 |
279 Court St |
English |
Install chimney liner - COMPLETE
|
A&AF |
|
131 |
161 Cross St |
Freeman AC |
Safety inspection and repairs to basketball hoops
and batting cage - COMPLETE
|
SLF |
|
132 |
Cross St |
In Town Units 24 & 25 |
Interior & Exterior Renovations-complete.
Recommended revisions: clean existing carpeting, repair siding, new
solid material in basement windows, replace 2nd floor non-functioning windows, new exterior lights, new
front steps, remove porch, paint exterior, seal fireplaces, new stove and new blinds, replace retaining wall.
- COMPLETE
|
SLF |
|
133 |
Cross St |
In Town Units 26 & 27 |
Interior & Exterior Renovations-complete.
Recommended revisions: clean existing carpeting, repair siding, new
solid material in basement windows, replace 2nd floor non-functioning windows, new exterior lights, new
front steps, remove porch, paint exterior, seal fireplaces, new stove and new blinds, repair front entrances,
repair concrete. - COMPLETE
|
SLF |
|
134 |
Wyllys St |
North Field |
Replace fence - COMPLETE
|
SLF |
|
136 |
255 Pine St |
Physical Plant |
Replace fuel oil tank - COMPLETE
|
A&AF |
|
137 |
171 Church St |
Religion |
Install chimney liner - COMPLETE
|
A&AF |
|
138 |
300 High St |
Romance Languages |
Install chimney liner - COMPLETE
|
A&AF |
|
139 |
265 Church St |
Science Center |
Engineering analysis of retaining wall
- COMPLETE
|
A&AF |
|
140 |
229 High St |
South College |
Replace casement window in President's Office
- COMPLETE
|
A&AF |
|
141 |
284 High St |
Women's Studies |
Install chimney liner - COMPLETE
|
A&AF |
|
142 |
190 High St |
WSA |
Install chimney liner - COMPLETE
|
A&AF |
|
143 |
109 Cross St |
109 Cross St |
House to remain vacant - COMPLETE
|
SLF-WF |
|
144 |
95 Pearl St |
Center for Humanities |
General Major Maintenance - COMPLETE
|
A&AF |
|
145 |
255 High St |
Center for the Americas |
Replace
condensate return lines - COMPLETE |
A&AF |
|
146 |
255 High St |
Center for the Americas |
Re-deck porch, rebuild railing -
COMPLETE
|
A&AF |
|
147 |
171 Church St |
Religion |
Replace condensate return lines |
A&AF |
|
148 |
350 High St |
Russell House |
Install chimney liner - COMPLETE
|
A&AF |
|
149 |
265 Church St |
Science Center |
Replace isolation valves |
A&AF |
|
150 |
265 Church St |
Science Center |
Rebuild AHU's - COMPLETE
|
A&AF |
|
151 |
265 Church St |
Science Center |
Engineering Analysis for repair of retaining wall
- COMPLETE
|
A&AF |
|
152 |
Church St |
Davenport Campus Center |
Add Floor Drain to Mens Room on 2nd Fl
- COMPLETE
|
SLF |
|
153 |
Church St |
Davenport Campus Center |
Replace Tile Floor in Grille Area -
COMPLETE
|
SLF |
|
154 |
Foss Hill |
Foss 4 |
Repair walk at north west entrance -
COMPLETE
|
SLF |
|
155 |
161 Cross St |
Freeman AC |
Wesleyan Arena chiller investigation and maintenance
- COMPLETE
|
SLF |
|
156 |
161 Cross St |
Freeman AC |
Irrigate Lower Long Lane 2 Field -
COMPLETE
|
SLF |
|
157 |
202 Washington St |
Gingerbread House |
Repair walk - COMPLETE
|
SLF |
|
158 |
Cross St |
In Town Units 22 & 23 |
Interior & Exterior Renovations-complete.
Recommended revisions: clean existing carpeting, repair siding, new
solid material in basement windows, replace 2nd floor non-functioning windows,
new exterior lights, new stove and new
blinds, repair concrete, curbs and walks, replace powder room (22) and entry
floors (22/23). - COMPLETE
|
SLF |
|
159 |
330 High St |
University Relations |
Paint exterior - COMPLETE
|
A&AF |
|
160 |
66 Home Ave. |
66 Home Ave. |
Replace fence - COMPLETE
|
SLF-WF |
|
161 |
69 Fountain |
69 Fountain |
Repair Stucco Walls, New Roof, Paint House, Repair
Porches - COMPLETE
|
SLF-WF |
|
162 |
70 Wyllys St |
Admissions |
Repairs to interior walls & ceilings
- COMPLETE
|
A&AF |
|
163 |
356 Washington St |
Armstrong Annex |
Repair & Repaint Exterior -
COMPLETE
|
A&AF |
|
164 |
Lawn Ave |
Butterfield A&B Lounge |
Remove Curtains & Replace Flooring in Kosher Kitchen
Area - COMPLETE
|
SLF |
|
165 |
280 William St |
CPP |
Engineering analysis of turbine generator
-COMPLETE |
Infrastructure |
|
166 |
301 High St |
DAC CarHS photo studio |
Replace carpet, paint - hallway and gallery
- COMPLETE
|
A&AF |
|
167 |
Church St |
Davenport Campus Center |
Replace Interior Glass Doors on Gr. Fl. |
SLF |
|
168 |
Foss Hill |
Foss 5 |
Repair wall-south side |
SLF |
|
170 |
Lawn Ave |
Greenhouse |
Repair walk
- COMPLETE |
A&AF |
|
171 |
McMonaughy Dr |
Mocon |
Carpet Offices - COMPLETE
|
SLF |
|
172 |
237 Church St |
Shanklin |
Repair granite steps - COMPLETE
|
A&AF |
|
173 |
318 High St |
University Relations |
Exterior repairs & paint - COMPLETE
|
A&AF |
|
174 |
230/240/256 Washington Street |
230/240/256 Washington Street |
Repave alley way behind these buildings
- COMPLETE
|
SLF |
|
175 |
Wyllys St |
Alumni/Fayerweather |
Paint exterior - COMPLETE
|
SLF |
|
176 |
140 Church St |
Barn |
Pave Parking area - COMPLETE
|
RP |
|
177 |
Campus |
Campus |
Continue campus rekeying |
A&AF |
|
178 |
283 Washington Terr |
CFA C World Music |
Humidity Control-Phase I - COMPLETE
|
A&AF |
|
179 |
285 Court St |
English |
Electrical service upgrade/support classroom
initiative - COMPLETE
|
A&AF |
|
180 |
Wyllys St |
Fayerweather Gym |
Repair skylight above drum room |
SLF |
|
181 |
Foss Hill |
Foss 6 |
Widen/repair walk
- COMPLETE |
SLF |
|
182 |
Lawn Ave |
Hall Atwater |
Replace
reverse osmosis system - COMPLETE |
A&AF |
|
183 |
265 Church St |
Science Center |
Repair bank/install steps to Lawn Ave. houses |
A&AF |
|
184 |
77 Pearl St |
University Relations |
Exterior work to preserve building, library
upgrades - COMPLETE
|
A&AF/RP |
|
185 |
281 High St |
Anthropology |
General Major Maintenance - COMPLETE
|
A&AF |
|
187 |
Lawn Ave |
Butterfield Dorms |
Replace shrubs. |
SLF |
|
188 |
283 Washington Terr |
CFA |
Pave worn corners of walks and replace lighting
- COMPLETE
|
A&AF |
|
189 |
283 Washington Terr |
CFA F Music Studios |
Paint interior throughout - COMPLETE
|
A&AF |
|
190 |
Church St |
Davenport Campus Center |
Replace Carpeting in Post Office -
COMPLETE
|
SLF |
|
191 |
301 High St |
Davison Art Center |
Repair/replace bluestone walk and site lighting
- COMPLETE
|
A&AF |
|
192 |
64 Harbor Dr |
Macomber Boat House |
Install heating system in lower garage bays-
COMPLETE
|
SLF |
|
193 |
McMonaughy Dr |
Mocon |
Replace Tile Throughout Kitchen Area -
COMPLETE
|
SLF |
|
194 |
238 Church St |
PAC |
Replace pneumatics w/DDC - COMPLETE
|
A&AF |
|
195 |
300 High St |
Romance Languages |
Paint windows, doors & trim -
COMPLETE
|
A&AF |
|
196 |
41 Lawn Ave |
Upward Bound |
Install Danfoss valves on radiators -
COMPLETE
|
A&AF |
|
197 |
167/169 High St |
Argus |
General Major Maintenance - COMPLETE
|
A&AF |
|
198 |
Lawn Ave |
Butterfield A&B Lounge |
Renovate Lounge Space |
SLF |
|
199 |
283 Washington Terr |
CFA L Art workshop 006 |
Replace existing casework - COMPLETE
|
A&AF |
|
203 |
Washington Terr |
CFA M Zilkha Photo Shop |
Replace Casework - COMPLETE
|
A&AF |
|
204 |
Foss Hill |
Foss 7 |
Repair wall-west side |
SLF |
|
205 |
Foss Hill |
Foss 7 |
Repair wall-north end |
SLF |
|
206 |
161 Cross St |
Freeman AC |
Upgrade irrigation on baseball field -
COMPLETE
|
SLF |
|
207 |
283 Washington Terr |
CFA P Theater |
Jackhammer on north east corner for the drain
- COMPLETE
|
A&AF |
|
208 |
Church/Pine |
Foss 8 Lounge |
Renovate Lounge Space |
SLF |
|
209 |
283 Washington Terr |
CFA G Art Studio So. Woodshop |
Ceiling mtd. reel type power cords -
COMPLETE
|
A&AF |
|
210 |
283 Washington Terr |
CFA M Zilkha Gallery |
Perform needs evaluation of gallery
lighting, flooring and window treatments. |
A&AF |
|
211 |
Church St |
Davenport Campus Center |
Miscellaneous painting |
SLF |
|
212 |
McMonaughy Dr |
Mocon |
Upgrade Sound System - COMPLETE
|
SLF |
|
213 |
110 Mount Vernon |
Wes Press |
Paint exterior - COMPLETE
|
A&AF |
|
214 |
Foss Hill |
Foss 4 |
Repave patio w/asphalt and bluestone edge
- COMPLETE
|
A&AF |