Building Name |
Building Address |
Proposed Maintenance |
Building Use |
|
Butterfield A/B/C |
Lawn/Huber Ave. |
Install 200 new stop valves on
flushometers. |
SLF |
|
Butterfield A/B/C |
Lawn/Huber Ave. |
Rebuild 3 existing cantilevered concrete
fire escape landings with steel landings and stairs. |
SLF |
|
Butterfield B |
20 Huber Ave. |
Install Magnetic hold open devices on all
stairwell/corridor doors, relocate 3 pull stations and horn/strobes. |
SLF |
|
Butterfield C |
50 Huber Ave. |
Install fog separators on Summerfields
kitchen drainage. Traps must be installed on inside of kitchen area at
floor drains and outside on sanitary line. May require excavation and site
repair. |
ADM |
|
Campus Classrooms |
Campus wide |
Address non-traditional teaching spaces as
budget allows: CFA RH105, CFA Crowell Green Room, DAC Photo Studio. |
ACAD |
|
Campus roofs |
Campus wide |
Install OSHA fall protection gates at
unprotected roof hatches and skylights. Areas to be prioritized by
need. Installation of gates will protect workers from falling through
opening. |
CAMPUS |
|
Campus wide |
Campus wide |
Cut trees back away from buildings, and
remove potential dangerous trees in all areas, including rentals. |
INFRA |
|
Campus Wide |
Campus wide |
Placeholder to address areas of concern
raised by students from lighting tour performed 11/1/06. |
SLF |
|
Campus Wide |
Campus wide |
Funding for annual roof maintenance
contract. |
SLF |
|
CAMS |
255 High St. |
Remove and replace the side flat roof area.
Replace gutters, install gutter caps. Patch and paint ceiling in
classroom below. |
ACAD |
|
CFA - AS South, AS North |
283 Washington Terr. |
Clean, repoint as needed, replace caulk and
backer rod joints and waterproof CFA Art Studio North and CFA Art Studio
South, Crowell Concert Hall, Rehearsal Hall, Music Studios and World
Music. |
ACAD |
|
CFA A - Rehearsal hall |
283 Washington Terr. |
Replace existing flat roof with new
University specified roof. |
ACAD |
|
CFA B - Crowell Concert |
283 Washington Terr. |
Replace existing flat roof with new
University specified roof. |
ACAD |
|
CFA C - World Music |
283 Washington Terr. |
Replace existing security divider/folding
partition that is used to prevent access to Gamelan to include motorized
operation. |
ACAD |
|
CFA F - Music Studios |
283 Washington Terr. |
Replace existing flat roof with new
University specified roof. |
ACAD |
|
CFA L - Art Workshops |
283 Washington Terr. |
Water infiltration in CFA screening room in
basement of Art Workshops. Water observed penetrating through wall. |
ACAD |
|
CFA M - Zilkha |
283 Washington Terr. |
Replace 4 frozen valves and reinsulate
valve station. |
ADM |
|
CFA P - Theater |
283 Washington Terr. |
Replace flying light rigging assembly.
Existing is bent and has electrical issues to include improperly sized
conductors, inadequate grounding and stripped screws. |
ACAD |
|
CFA R - Dance Studio |
283 Washington Terr. |
Replace existing flat roof with new
University specified roof. |
ACAD |
|
CPP |
280 William St. |
Re-gasketing of chiller no. 2 is required. |
INFRA |
|
CPP |
280 William St. |
Clean internal components of boilers no. 1,
2, and 3 and the economizer. |
INFRA |
|
CPP |
280 William St. |
Replace existing gas control valves that
control gas flow to boilers #1, and #2. |
INFRA |
|
CPP |
280 William St. |
Replace roof below surface. The roof, which
is original to the building’s construction in 1971, has active leaks.
Includes lighting, sidewalks and stairs. |
INFRA |
|
Davison Health Center |
327 High St |
Install magnet hold opens on the 2
corridor doors and basement door to eliminate propping open these doors. Connect to
existing fire alarm system. |
ADM |
|
Davison Health Center |
327 High St. |
Install exterior screens on all operable
windows in Health Center Infirmary on first floor to prevent bug
infiltration to this area. |
ADM |
|
Faculty/Staff |
148 Church St. |
Replace entire roof, gutters, leaders,
etc,. Exterior carpentry. Reflash chimney and repair as necessary. |
RP |
|
Faculty/Staff |
Campus wide |
Contingency to perform boiler replacements
where needed. |
RP |
|
Fisk Hall |
262 High St. |
Prep and paint fires escapes located on
east side of building. Inspect and resecure as needed. |
ACAD |
|
Foss 1-10 |
Foss Hill Dr. |
Install approximately 100 Symmons 1-100 X
dimension shower valves with integral stops |
SLF |
|
Freeman Athletic Center |
161 Cross St. |
Annual maintenace of athletic fields. |
ATH |
|
Freeman Athletic Center |
161 Cross St. |
Air quality in ERG room is poor while
working out. Modify existing control sequence, increase air flow to
maximum unit can handle. |
ATH |
|
Hall Atwater/Shanklin |
237 Church St. |
Install permanent wiring fed from emergency
generator to power 3rd floor fish lab and 4th floor Shanklin labs. |
ACAD |
|
High Rise |
110 Church St. |
Install new elevator door controls. This
upgrade will enhance elevator operation and synchronize with elevator
modernization performed MM04. |
SLF |
|
High Rise |
110 Church St. |
Repipe discharge line from relief valve to
location away from fresh air intake. |
SLF |
|
High Rise |
110 Church St. |
Renovate Kitchens and bathrooms in each
apartment on the 6th and 7th floors. Total renovations include kitchens
& bathrooms same scope as Low-rise B), replace base molding throughout
and paint entire unit (ceilings included). Possible replacement of
hallway carpeting, paint corridor walls/ceilings, replace common area
lighting. Demo closet in existing 2-bed units and install new ceiling
lighting in common area. Install wall hung counters to eliminate kitchen
tables. Install sprinkler heads in new units. Replace all ceiling
lighting. Install new wall switch in new location in newly created
bedrooms. Replace all smoke detectors with new. Replace existing t-stats
with lite-stats. Install access panels and shut offs for all supplies in
chases in bathrooms and kitchens. |
SLF |
|
Neighborhood Pre-school |
115 High St. |
Replace roof and gutters, leaders &
downspouts. Reflash chimney and repair as necessary. Requires
abatement. |
RP |
|
Non-Traditional Dorm / Program House |
Foss Hill Dr. |
Shower pans on the third floor of Foss 9
are actively leaking all the way down to the boiler room. Replace or
repair shower pans in all bathrooms. Alternative repair: trowel applied
epoxy. |
SLF |
|
Non-Traditional Dorm / Program House |
Gingerbread House - 202 Washington St. |
Replace 11 windows in newer section of
facility. Redesign opening to accept a more secure and energy efficient
window. Paint all new wood and existing structure to match. Install
security screens on first floor. |
SLF |
|
Non-Traditional Dorm / Program House |
Green House - 230 Washington St. |
Provide electrical, plumbing and venting to
accommodate new washer and dryer.
Replace carpeting in all corridors, lobbies and common rooms. |
SLF |
|
Non-Traditional Dorm / Program House |
La Casa - 240 Washington St |
Replace all storm windows with new storm
windows. Weatherproof west side porch. |
SLF |
|
North College |
237 High St. |
Remove mechanical system in mechanical room
to include all piping, pumps, valves and related system and install
new. Install new piping, valves, insulation, and direct digital
controls (RCMS). Paint walls and floor and replace lighting. |
ADM |
|
Olin Library |
252 Church St |
Replace chiller in Special Collections. |
ACAD |
|
Olin Library |
252 Church St |
Existing pumps have no operable service
valves or check valves. Repipe pumps to accommodate the equipment. |
ACAD |
|
President's House |
269 High St |
Paint all exterior wood trim to match
existing. Adhere to state and federal requirements for lead paint
removal. Perform stucco repair and paint repaired areas to match
existing. |
ADM |
|
Science Center |
265 Church St. |
Retaining wall on north side of loading
dock of the Science Center has signs of horizontal and vertical cracking
with signs of seepage and leaking from behind the surface. Upper portion
of wall has signs of deflection. |
ACAD |
|
Science Center |
265 Church St. |
Install metal security fencing at stair
landings (7) that open to center building areaway. |
ACAD |
|
Science Tower |
265 Church St. |
Phase in installation of new fire alarm
system in Science building and Science Tower. Phase 1 to include Lobby
level, including SC 150, Pi Cafe, computer lab and classrooms. |
ACAD |
|
Shanklin |
265 Church St. |
Renovate mens and womens bathrooms on the
fourth floor of the Shanklin building. Complete demolition is required.
Replace fixtures and seal floor of all penetrations. |
ACAD |
|
South College |
229 High St. |
Replace entire electrical service (main
distribution) supporting South College. Address mechanical units to
repair leaks. |
ADM |
|
South College |
229 High St. |
Install a new addressable fire alarm system
for entire building with smoke detectors, pull stations and horn/strobes
on each floor. Patch, paint. Conceal all wiring. |
ADM |
|
Student WF |
186 Washington St. |
Replace existing roofing system down to
deck and replace with fully adhered EPDM roofing system; first floor
kitchen area. |
SLF-WF |
|
Student WF |
188 Cross St. |
Upgrade electrical service, wiring and
receptacles so that all outlets are grounded. Remove knob and tube. |
SLF-WF |
|
Student WF |
2 Warren St. |
Replace porch, stairs and overhang with
new. |
SLF-WF |
|
Student WF |
203 A&B Pine St. |
Complete renovation of interior and
exterior of 2-family woodframe to include renovations (kitchens,
bathrooms, floors, windows, interior and exterior paint, vinyl siding). |
SLF-WF |
|
Student WF |
21 Vine St. |
Replace existing wood windows and storm
windows with new insulated glass wood windows and full screens. Provide
trim repair/replacement. Caulk, prime and paint. Install new windows
shades. |
SLF-WF |
|
Student WF |
223 Pine St. |
Remove existing shingle roofing system and
install new 30 year shingle roofing system. |
SLF-WF |
|
Student WF |
266 Pine St. |
Remove 2/3 of the concrete landing and 4
stairs and replace with concrete. |
SLF-WF |
|
Student WF |
65 Pearl St. |
Remove the present shingle roofing system
and install new 30 year shingle roof system. Replace gutters, install
gutter caps. |
SLF-WF |
|
Student WF |
96 A&B Lawn Ave. |
Provide first floor kitchen/bath complete
renovation, includes all trades. Investigate plumbing from second floor
for possible leaks. Renovate porches. Install sprinklers and fire alarm
system.
Coordinate with independent fire alarm and sprinkler installation. |
SLF-WF |
|
Student WF |
97 Lawn Ave. |
Rebuild front/side porches in toto. Address
retaining wall. |
SLF-WF |
|
Student WF |
Campus wide |
Insulate attics of select houses. |
SLF-WF |
|
Student WF |
Campus wide |
Allowance to clean wood frame gutters.
Blocked gutters causes to back up under roof and into house causing
damage. Locations to be addressed on an as needed basis. |
SLF-WF |
|
Student WF |
Campus wide |
Replace old windows w/energy efficient
windows and full screens. Houses to be identified and selected. |
SLF-WF |
|
Student WF |
Campus wide |
Repair steps and landings at various
woodframe houses. |
SLF-WF |
|
Student WF |
Campus wide |
Contingency to replace old furnaces in 7-8
houses as they fail due to age and condition. |
SLF-WF |
|
Student WF |
Campus wide |
Identify woodframe houses that require
plumbing repairs (leaks, uninsulated pipes, poorly functioning water
heaters, etc). |
SLF-WF |
|
Student WF |
Campus wide |
Many houses have lights that are
permanently on 24/7. Install switches or motion sensors on all common
area fixtures. Wiring will be required. |
SLF-WF |
|
Student WF |
Campus wide |
Upgrade electrical services on selected
houses to provide new wiring and grounded outlets. |
SLF-WF |
|
Student WF |
Campus wide |
Allowance for storm window replacements
during summer maintenance evaluation. |
SLF-WF |
|
Student WF |
Campus wide |
Replace rotted basement hatchways -
allowance |
SLF-WF |
|
University Relations |
318 High St. |
Repair/patch/paint walls in lobby and
stairwell to 3rd floor. |
ADM |
|
Woodframe / Non-Traditional Dorm / Program
House |
Campus wide |
Replace non-functioning kitchen appliances;
annual allowance. |
SLF-WF |