| Building Name/Address |
Description
|
Managed by |
Work Schedule |
| North College - 237 High St |
Flat roof replacement |
Roseann Sillasen |
5/27/2009 - 6/19/2009 |
| Woodframes/Non Traditional & Traditional Dorms |
Annual allowance to paint interiors of student woodframes, program houses and dorms during summer maintenance |
Tom Policki |
5/26/2009 - 8/30/2009 |
| 272-278 Court St |
Scrape, prep and paint all ext. surfaces including all windows, doors, soffits, columns and all trim. Perform masonry repairs. Trim trees. |
Roseann Sillasen |
5/26/2009 - 8/30/2009 |
| Neighborhood Pre-School - 20 Lawn Ave |
Replace roof |
Roseann Sillasen |
Summer 2009 - to be coordinated with building occupants |
| 107 Cross St |
Replace kitchen floor, install new kitchen cabinets, repair walls, install new sink. Bathroom needs to be enlarged and updated. |
Roseann Sillasen |
5/26/2009 - 8/1/2009 |
| 1 - 5 Vine |
Replace cement stairs and patio leading from Vine St to laundry- deteriorated |
Dave Hall |
6/3/2009 - 7/15/2009 |
| 2 Warren |
Replace roof / paint exterior |
Roseann Sillasen |
5/28/2009 - 6/10/2009 |
| Freeman Athletic Center - 161 Cross St |
Replace 3 meter diving standards with new diving platform |
Jeff Sweet / Roseann Sillasen |
8/1/2009 - 8/30/2009 |
| CFA C - World Music - 283 Washington Terr |
Replace eroded stairs on north side of building |
Roseann Sillasen |
6/3/2009 - 7/15/2009 |
| 283 Washington Terr |
Safety Item. Inspect all rigging in Theater; prioritize, phase and execute repairs. Inspect and repair bridge panel motors. Motors leak oil. |
Roseann Sillasen |
Summer 2009 |
| 43 Fountain Ave |
Porch roof replacement. Carpentry and stucco repairs. Exterior paint. |
Roseann Sillasen |
5/26/2009 - 7/15/2009 |
| 28 Lawn Ave |
Replace windows. Perform soffit repair |
Roseann Sillasen |
6/3/2009 - 7/15/2009 |
| 55 Brainard - 1st floor |
Replace front porch; failing. Concrete work on walkway needed. Replace roof, gutters, chimney repointing. |
Roseann Sillasen |
6/3/2009 - 8/1/2009 |
| Center For the Arts - 283 Washington Terr |
Install blue light phone in south courtyard next to CFA Music Studio |
Roseann Sillasen |
5/26/2009 - 7/15/2009 |
| Gingerbread House - 202 Washington St |
Reno 2nd floor bathroom. |
Roseann Sillasen |
Perform Summer 2009 |
| Gingerbread House - 202 Washington St |
Roof replacement |
Roseann Sillasen |
5/27/2009 - 6/12/2009 |
| 63 A&B Lawn Ave |
Roof replacement, new window installations |
Roseann Sillasen |
6/1/2009 - 7/15/2009 |
| 48 Home Ave |
Fixed storm install on porch windows |
Roseann Sillasen |
6/10/2009 - 7/3/2009 |
| 23 Vine St / 215 Pine St |
Basement hatchway replacement |
Roseann Sillasen |
6/10/2009 - 7/15/2009 |
| 42 Miles |
Kitchen upgrade |
Roseann Sillasen |
6/3/2009 - 7/31/2009 |
| 239 Pine St |
Replace front porches, ceilings and paint as required. |
Roseann Sillasen |
6/1/2009 - 8/1/2009 |
| 230 Washington St |
Remove hallway cabinet; provide additional shelving |
Roseann Sillasen |
6/3/2009 - 6/30/2009 |
| Undergrad Woodframes |
Install over range hood fans - various locations |
Roseann Sillasen |
6/3/2009 - 7/31/2009 |
| 237 High Street |
Roof replacement |
Roseann Sillasen |
5/27/2009 - 6/19/2009 |
| Butterfield C - 50 Huber Ave |
Address rain run off from parking area at 51 Lawn Ave. |
Dave Hall |
5/26/2009 - 6/15/2009 |
| 128 Church St |
Replace porch roof. |
Roseann Sillasen |
5/27/2009 - 6/1/2009 |
| 10 Knowles Ave |
Install new windows; insulate attic |
Roseann Sillasen |
6/15/2009 - 6/25/2009 |
| CAMS - 255 High St |
Replace rubber roof over classroom |
Roseann Sillasen |
6/1/2009 - 6/6/2009 |
| Central Power Plant - 280 William St |
Install valves on feed-water piping to isolate boilers |
Peter Staye |
Summer 2009 |
| Romance Languages - 300 High St Basement |
Minor bathroom upgrade |
Brandi Hood |
Summer 2009 - to be coordinated with occupants |
| CAAS - 343 High St |
Install trench drains in basement |
Roseann Sillasen |
Summer 2009 - to be coordinated with occupants |
| |
|
|
|
| 34 Fountain Ave |
Replace Kitchen floor. Install plywood subfloor. |
Roseann Sillasen |
Summer 2010 |
| 131 Cross St |
Paint house. Repair side porch and install new steps per code. Install new basement door and trim back trees. |
Roseann Sillasen |
Summer 2010 |
| Butterfield A/B - Lawn/Huber Ave |
Clean all duct work in facility |
Mike Conte |
Summer 2010 |
| Olin Library -s 252 Church St |
Install code compliant speaker notification appliances in all areas, including stacks; add smoke detectors as necessary. |
Barbara Spalding |
Summer 2010 |
| Upward Bound - 41 Lawn Ave |
Paint exterior of entire building. Replace rear porch. Perform carpentry work to front porch. Replace front stairs and install new railings. |
Roseann Sillasen |
Summer 2010 |
| Freeman Athletic Center - 161 Cross St |
Remove existing wood siding, waterproof, install new wood siding, paint. |
Roseann Sillasen |
Summer 2010 |
| Campus wide |
Campus Landscape Plan - Hardscapes (Year 6 of 7) |
Roseann Sillasen |
Summer 2010 |
| Asian / Asian American - 107 High St |
Paint House. Remove front porch stairs, replace the decking as required. Replace railings, increase height per Code. Replace steps. |
Roseann Sillasen |
Summer 2010 |
| 146 Cross St |
Replace rotted wood siding. Prep and paint entire house. |
Roseann Sillasen |
Summer 2010 |
| 267 Court St |
Paint exterior. Repair wood soffits and wood details. Install new gutters and leaders. |
Roseann Sillasen |
Summer 2010 |
| 251 Pine St - 2 Family |
Replace windows; renovate porches, vinyl side exterior. |
Roseann Sillasen |
Summer 2010 |
| Van Vleck Observatory - 11 Foss Hill Dr |
Replace roof on northwest side of building over computer area. |
Tom Policki / Roseann Sillasen |
Summer 2010 |
| 2 Warren St |
Existing 3 bed house requires total interior renovation. Electrical/plumbing throughout to be replaced. Update fire alarm, lighting. |
Roseann Sillasen |
Summer 2010 |
| 161 Cross St |
Paint all paintable exterior surfaces including the Dryvit surfaces. Initiate work at northeast elevations. Carpentry reparis at soffits |
Roseann Sillasen |
Summer 2010 |
| 235 Pine St |
Rebuild/Repair front porch, paint front and rear porches |
Roseann Sillasen |
Summer 2010 |
| 134 Cross St |
Reno existing 5 bedroom house. New electrical/ plumbing. Reuse fire alarm system. |
Roseann Sillasen |
Summer 2010 |
| Foss Hill 8 - Foss Hill Dr |
Replace stone steps and railing with cast concrete. |
Dave Hall |
Summer 2010 |
| CFA M - Zilkha - 283 Washington Terr |
Replace exterior concrete stairs. |
Roseann Sillasen |
Summer 2010 |
| Cross St (Fountain to Warren) |
Replace sidewalk and provide brick apron between new walk and road similar to brick work at NE entrance to Freeman addition. |
Dave Hall / Roseann Sillasen |
Summer 2010 |
| 269 Pine Av |
Reno 3 bed house to a 4 bed house. Remove 2nd floor kitchen. |
Roseann Sillasen |
Summer 2010 |
| Butterfield A - 20 Lawn Ave |
Install new fire alarm system; eliminate battery smoke detectors. Phased project. |
Barbara Spalding |
Summer 2010 |
| 7 Fountain Ave |
Paint Exterior. Replace porch and main roof. |
Roseann Sillasen |
Summer 2010 |
| 156 High St |
New security card access control system. |
Roseann Sillasen |
Summer 2010 |
| 127 Cross St |
Repair stucco; paint exterior. Replace gutters and aluminum soffit wrap. |
Roseann Sillasen |
Summer 2010 |
| German Hausa - 135 High St |
Renovate house |
Roseann Sillasen |
Summer 2010 |
| Butterfield B - 20 Huber Ave |
Renovate the stone and asphalt dumpster area and install fencing. Install pad for 8 yard dumpster and elongate curb cut. |
Dave Hall |
Summer 2010 |
| CFA P - Theater - 283 Washington Terr |
Repair theatrical lighting system. Existing electrical cabling is very old. |
Roseann Sillasen |
Summer 2010 |
| 211 Pine St |
Replace windows and repair concrete header on second floor above windows on east elevation. |
Roseann Sillasen |
Summer 2010 |
| 264 Court |
Replace front side, rear porch, stairs, windows, roof, gutters. Paint exterior of house. |
Roseann Sillasen |
Summer 2010 |